United Utilities HQ, Haweswater House, Lingley Mere

Roles;
Design & Project Manager

United Utilities occupy a large campus site featuring many different buildings which were built between 25-30 years ago, and now requiring reconfiguring and updating.
Haweswater House is divided into three adjoining buildings, and the works for this phase were approx 50,00ft sq, containing the call centre, security centre, incident room and management offices. Required works included the design and construction of a complete interior refurbishment including replacement of mechanical and electrical systems.
Complications on the project included the client’s retained occupation of some departments within the designated working areas, for longer than originally intended, causing some delays to the programming of the work.